GHADIR 674

Project Status

Stay updated on the construction progress of Ghadir 674.

In Progress

Tiling In Progress

MEP systems installed, painting and false ceilings completed. Tiling is currently underway, with aluminum windows and doors, followed by woodwork, still ahead.

Upcoming

Q4 2026 Delivery

Apartments will be delivered by Q4 2026. Reserve your unit today.

Construction Progress

Overall Completion~80%

Project Timeline

Major Milestones

Completed

Site Preparation & Excavation

2019

Land clearing, excavation, and foundation groundwork completed.

Completed

Structural Construction

2020 – 2022

Reinforced concrete structure for all 6 stories and 2 underground parking levels completed.

Completed

Exterior Envelope & Façade

2023

Building envelope, exterior cladding, windows, and balcony installations finished.

Completed

MEP, Painting & False Ceilings

2024 – 2025

Mechanical, electrical, and plumbing systems installed. Painting and false ceilings completed across all units.

In Progress

Tiling

2025 – 2026

Tiling work is currently in progress across all apartments and common areas.

Upcoming

Aluminum Windows, Doors & Woodwork

2026

Following tiling completion, aluminum windows and doors will be installed, followed by woodwork finishing.

Upcoming

Final Inspections & Delivery

Q4 2026

Quality assurance inspections, final touch-ups, and apartment handover to owners.

Ghadir 674 construction progress

See the Latest Progress